Where the water can go
Surface water or the ground
A discharge to a watercourse or to ground may require a water discharge activity or groundwater activity permit in England, depending on the nature of the discharge and any applicable exclusions or regulatory positions. The Environment Agency guidance on discharge permits explains the requirements.
For certain construction excavations, RPS 261 addresses short term discharges of uncontaminated water, wholly or mainly rainwater, to surface water. The statement applies only where its conditions are met, including restrictions on discharge duration, water quality, receiving waters and site activities. It does not apply to discharges to ground or groundwater. It also does not remove the underlying legal requirement for a permit, but explains when the Environment Agency will not normally take enforcement action.
Where contaminated groundwater or water from contaminated land is pumped out for treatment before discharge, RPS 261 states that a bespoke water discharge activity permit is required. That pump and treat case belongs with groundwater remediation rather than routine construction dewatering.
The public sewer
Discharging to the foul or combined sewer requires consent from, or an agreement with, the sewerage undertaker where the discharge is classed as trade effluent. The trade effluent consent process can establish conditions for flow rate, volume and composition. The proposed pumping and treatment arrangements need to accommodate those conditions throughout the discharge.
Tankering off site
Tankering may be needed where the water is oily, chemically contaminated or too variable to treat at the excavation. Whether the material is legally classified as waste depends on its characteristics and circumstances. Where it is waste, the relevant duty of care, waste classification, carrier registration and receiving facility requirements apply. Contaminated water disposal covers this separate service.
Abstraction licensing and exemptions
Taking the water out is a separate question from putting it back. In England, abstraction of more than 20 cubic metres a day is likely to need a licence from the Environment Agency. There are exemptions for certain small scale dewatering activities undertaken to prevent interference with building or engineering works. The groundwater exemption under regulation 5 of the Water Abstraction and Impounding (Exemptions) Regulations 2017 includes conditions concerning the duration of abstraction and excludes abstraction from wells or boreholes. Surface water abstraction has separate exemption provisions.
A further regulatory position statement, RPS 368, covers qualifying small scale groundwater abstraction for construction dewatering where there is a high water table, for less than 270 days. Its conditions must be checked separately from the statutory exemptions. The Environment Agency abstraction licensing guidance explains the current position.
Scotland, Wales and Northern Ireland have separate regulatory arrangements. In Scotland, water activities are regulated by the Scottish Environment Protection Agency. The relevant national regulator and consent requirements need to be identified for the site rather than applying the English exemption rules across the UK.
Monitoring while the system runs
Standpipes and piezometers inside and outside the works show whether the drawdown is being achieved and how far it extends. Flow meters on the discharge show what is actually being pumped, which matters for both the licence position and the treatment plant sizing. Sampling at the agreed point covers the consent conditions.
- Water levels at the dig and at monitoring points away from it
- Pumped volumes, by day and cumulatively
- Suspended solids and pH at the discharge point, plus any determinands named in the consent
- Ground and structure levels where settlement is a concern
- Plant running hours, standby pump checks and fuel or power supply
Shutting the system down
Groundwater returns when pumping stops, and recovery needs to be considered alongside the permanent works. Shutting down in stages, with levels watched between steps, helps identify whether buoyancy, flooding of ducts or seepage into the structure could become a problem. Wells and wellpoints are then decommissioned so that they do not remain as a pathway between water bearing layers, which matters most on a site with any history of contamination that a site investigation has already identified.