Dewatering controls groundwater and surface water so an excavation can be worked dry. The method and the discharge route are decided together, because where the water can lawfully go usually governs how the pumping is designed.

Dewatering Services quote

What dewatering controls on a site

Dewatering is the temporary control of groundwater and surface water so that an excavation, basement, shaft or remediation dig can be worked in dry and stable ground. Two problems usually have to be solved at once: water entering the excavation from the surrounding ground, and rainfall and run-off collecting inside it. The first depends on the permeability of the soils and the depth below the standing water level, the second on the catchment around the dig and the weather while the job runs.

The pumping arrangement is only half of it. The water has to go somewhere, and the receiving route decides how clean it must be, which consent or permit applies, and how much treatment plant has to stand on the site. The discharge arrangements and pumping design need to be considered together. Otherwise, a system may achieve the required drawdown but have no suitable authorised discharge outlet.

Person in a hard hat and high visibility vest using a tablet beside a water channel

Method follows the ground

Permeability, drawdown and duration decide between sump pumping, wellpoints, deep wells and ejectors.

Discharge route first

The receiving outlet determines permit or consent requirements and whether on-site treatment or off-site removal is needed.

Movement watched, not assumed

Drawdown outside the excavation is monitored where settlement could affect neighbouring structures.

Ground conditions and the choice of method

Particle size, permeability, the standing water level and the presence of any confined layer narrow the options before any equipment is considered. A ground investigation that was planned for foundation design will not always answer those questions, so the gaps are worth identifying early rather than discovering them when the pumps are running.

Sump pumping

Water is allowed to enter the excavation and is collected in a sump cut below formation level, then pumped out. It suits shallow digs in low permeability ground and short duration work. Its weakness is that water travels through the excavation face, which can wash fines out of the slope and soften the formation.

Wellpoints

A line or ring of closely spaced small diameter wells is connected to a header main and a vacuum pump, drawing the water table down ahead of the dig. Wellpoints work well in sands and sandy gravels and in trench work where the system can be advanced along the route. Drawdown from a single stage is limited by suction lift, so deeper excavations need staged installations.

Deep wells and ejectors

Deep wells with submersible pumps handle larger drawdowns and higher yields, and are commonly used for deep shafts and basements in permeable ground. Ejectors, which use a pressurised water loop to lift small flows from each well, suit silts and other low yielding soils where a submersible pump would run dry but pore pressure still has to be reduced.

Settlement and ground movement

Lowering groundwater increases effective stress in the soil, and in compressible layers, made ground or peat that can show as settlement at the surface. The risk is to neighbouring structures, buried services and highways as well as the excavation itself. It is assessed from the predicted drawdown around the works, not only at the dig.

Where the predicted movement matters, the scheme can be changed instead of accepted. Options include cutting off the flow with a physical barrier so less water has to be removed, recharging the aquifer away from the excavation to hold the water level up under sensitive buildings, or reducing the target drawdown and dealing with the residual water in the excavation. Precise levelling and pore pressure monitoring during the job show whether the prediction held.

Silt and suspended solids

Pumped water from an excavation is rarely clear at the start. Fines drawn in during initial pumping, disturbance at the sump and contact with fresh concrete all affect what arrives at the outfall. Suspended solids and pH can make a discharge unacceptable, alongside other contaminants identified through site assessment. Settlement tanks, lagoons, lamella separators and filtration can be used according to the particle size, flow and required water quality.

In England, the storage, treatment and use of construction site water containing suspended solids is addressed by Environment Agency RPS 235. It sets out the conditions under which the Environment Agency will not normally take enforcement action for operating without a waste permit. The statement does not remove separate discharge requirements, and water containing concrete is subject to different guidance. Treatment performance should be demonstrated by sampling the treated water, not assumed from the presence of the plant.

Gloved hand reaching into shallow flowing water at a river bank

Discuss dewatering for your site

Send the excavation depth, ground conditions and what is nearby, and the available discharge routes can be assessed with the pumping options.

Where the water can go

Surface water or the ground

A discharge to a watercourse or to ground may require a water discharge activity or groundwater activity permit in England, depending on the nature of the discharge and any applicable exclusions or regulatory positions. The Environment Agency guidance on discharge permits explains the requirements.

For certain construction excavations, RPS 261 addresses short term discharges of uncontaminated water, wholly or mainly rainwater, to surface water. The statement applies only where its conditions are met, including restrictions on discharge duration, water quality, receiving waters and site activities. It does not apply to discharges to ground or groundwater. It also does not remove the underlying legal requirement for a permit, but explains when the Environment Agency will not normally take enforcement action.

Where contaminated groundwater or water from contaminated land is pumped out for treatment before discharge, RPS 261 states that a bespoke water discharge activity permit is required. That pump and treat case belongs with groundwater remediation rather than routine construction dewatering.

The public sewer

Discharging to the foul or combined sewer requires consent from, or an agreement with, the sewerage undertaker where the discharge is classed as trade effluent. The trade effluent consent process can establish conditions for flow rate, volume and composition. The proposed pumping and treatment arrangements need to accommodate those conditions throughout the discharge.

Tankering off site

Tankering may be needed where the water is oily, chemically contaminated or too variable to treat at the excavation. Whether the material is legally classified as waste depends on its characteristics and circumstances. Where it is waste, the relevant duty of care, waste classification, carrier registration and receiving facility requirements apply. Contaminated water disposal covers this separate service.

Abstraction licensing and exemptions

Taking the water out is a separate question from putting it back. In England, abstraction of more than 20 cubic metres a day is likely to need a licence from the Environment Agency. There are exemptions for certain small scale dewatering activities undertaken to prevent interference with building or engineering works. The groundwater exemption under regulation 5 of the Water Abstraction and Impounding (Exemptions) Regulations 2017 includes conditions concerning the duration of abstraction and excludes abstraction from wells or boreholes. Surface water abstraction has separate exemption provisions.

A further regulatory position statement, RPS 368, covers qualifying small scale groundwater abstraction for construction dewatering where there is a high water table, for less than 270 days. Its conditions must be checked separately from the statutory exemptions. The Environment Agency abstraction licensing guidance explains the current position.

Scotland, Wales and Northern Ireland have separate regulatory arrangements. In Scotland, water activities are regulated by the Scottish Environment Protection Agency. The relevant national regulator and consent requirements need to be identified for the site rather than applying the English exemption rules across the UK.

Monitoring while the system runs

Standpipes and piezometers inside and outside the works show whether the drawdown is being achieved and how far it extends. Flow meters on the discharge show what is actually being pumped, which matters for both the licence position and the treatment plant sizing. Sampling at the agreed point covers the consent conditions.

  • Water levels at the dig and at monitoring points away from it
  • Pumped volumes, by day and cumulatively
  • Suspended solids and pH at the discharge point, plus any determinands named in the consent
  • Ground and structure levels where settlement is a concern
  • Plant running hours, standby pump checks and fuel or power supply

Shutting the system down

Groundwater returns when pumping stops, and recovery needs to be considered alongside the permanent works. Shutting down in stages, with levels watched between steps, helps identify whether buoyancy, flooding of ducts or seepage into the structure could become a problem. Wells and wellpoints are then decommissioned so that they do not remain as a pathway between water bearing layers, which matters most on a site with any history of contamination that a site investigation has already identified.

Dewatering Services: common questions

What is dewatering in construction?

It is the temporary removal and control of water so that excavation and construction can take place below the water table or in wet ground. It covers both groundwater flowing in through the sides and base of a dig and rainfall collecting within it, and it ends when the permanent works can resist the water on their own.

What dewatering methods are available?

Sump pumping, wellpoints, deep wells with submersible pumps, and ejector wells are the common choices, sometimes combined with a physical cut-off. Selection depends on soil permeability, how much drawdown is needed, how long the works last and how much movement neighbouring structures can tolerate.

How is a deep excavation dewatered?

Deep excavations in permeable ground may use deep wells outside the dig, with the spacing and pumping capacity determined by permeability, groundwater levels and the required drawdown. Wellpoints or ejectors may be more suitable in other ground conditions. Cut-off walls can also reduce inflows and limit groundwater movement outside the excavation.

Do I need a licence to pump water out of an excavation?

In England, abstraction above 20 cubic metres a day is likely to need a licence. Certain construction dewatering activities qualify for statutory exemptions, while RPS 368 covers qualifying small scale groundwater abstraction lasting less than 270 days. The source of the water, abstraction method, quantity, duration and applicable conditions determine which requirements apply.

Can dewatering water be discharged to a drain?

The receiving drainage system must first be identified. Discharge to a watercourse or surface water system may need an environmental permit, although RPS 261 provides a regulatory position for qualifying temporary discharges of uncontaminated water from excavations. Trade effluent discharged to a foul or combined sewer requires consent from, or an agreement with, the sewerage undertaker. Contaminated water may need treatment or off-site removal.

Is sludge dewatering the same thing?

No. Sludge dewatering is the removal of water from a solid or semi-solid material, usually with a filter press, centrifuge or geotextile bag, to reduce the volume sent for disposal. Site dewatering controls water in the ground so that excavation can proceed. The two are sometimes needed on the same job.